A subcontract term that conflicts with the Miller Act is ineffective in a suit against the surety on the payment bond. But, that right may be waived.

In United States ex rel. Marenalley Constr., LLC v. Zurich American Ins. Co., et al, Civil Action No. 14-4581 (E.D. Pa. March 13, 2015), a subcontractor filed suit under the Miller Act to recover against the prime contractor’s payment bond for additional work performed at the VA Medical Center in Philadelphia, PA. The Miller Act provides a subcontractor the right to bring suit against the surety that issued the prime contractor’s payment bond if the subcontractor is not paid within ninety days of the completion of its work.

Prior to the commencement of the action, the prime contractor sought additional compensation from the VA in an administrative proceeding, which included the additional compensation sought by the Subcontractor. The VA had not approved payment for the additional work at the time the subcontractor filed suit. The prime contractor and its surety moved to dismiss, or in the alternative, to stay the action pending the outcome of the prime contractor’s claim against the VA.

The court denied the motion to dismiss, and held that the administrative procedure between the prime contractor and VA provides no direct remedy to a subcontractor for any claim it has against the prime contractor. The Court explained, “When a subcontractor and prime contractor have a dispute about the amount due the subcontractor, that dispute is not resolved in the [administrative] proceeding.”

Finally, the Court refused to grant a stay. Citing to non-Miller Act cases, the prime contractor and surety argued that the surety’s liability is “derivative” of the prime contractors and the prime contractor’s liability is being determined in the administrative proceeding.  The Court disagreed, and explained that the surety’s “liability on a Miller Act bond must be at least coextensive with the obligations imposed by the Miller Act if the bond is to have its intended effect.” As such, “a subcontract term that conflicts with the Miller Act is ineffective in a suit against the surety on the payment bond.” The practical takeaway from this case is the reminder the Miller Act permits a subcontractor to seek payment against the payment bond once the requisite ninety-day period has elapsed regardless of other administrative procedures that may be contractually required. Those Miller Act rights, however, may be waived, if: (1) the waiver is in writing; (2) signed by the person whose right is waived; and (3) executed after the person whose rights are waived has furnished labor or materials for use in the performance of the contract.